Artifact: Critical Path — Checkout Redesign
Aurora Checkout Redesign -- critical path -- exercises co-04.
| Path | Sum (days) |
|---|---|
| 2.1 -> 2.2 -> 3.1 -> 3.2 -> 3.3 (critical) | 4+3+5+3+2 = 17 |
| 1.1 -> 3.1 -> 3.2 -> 3.3 | 3+5+3+2 = 13 |
| 1.2 -> 3.1 -> 3.2 -> 3.3 | 3+5+3+2 = 13 |
| 1.3 -> 3.1 -> 3.2 -> 3.3 | 2+5+3+2 = 12 |
| 2.1 -> 2.2 -> 2.3 | 4+3+2 = 9 |
Critical path: 2.1 Cart persistence rework -> 2.2 Order summary UI -> 3.1 E2E test suite -> 3.2 Load test -> 3.3 Feature-flag rollout, 17 working days, zero slack. Every other path carries slack relative to this one; delaying any task on the critical path by one day delays the project by one day.