Artifact: Sprint and Backlog Plan — Checkout Redesign

Aurora Checkout Redesign -- sprint and backlog plan -- exercises co-07.

SprintCommitted itemsPointsDependency check
Sprint 12.1 Cart persistence rework (8), 1.2 PayPal adapter (5)13Neither item has an unmet prerequisite.
Sprint 21.1 Stripe adapter (5), 1.3 Apple Pay adapter (3), 2.2 Order summary UI (3), 2.3 Order confirmation email (2)132.2 and 2.3 depend on 2.1, which finished in Sprint 1; 1.1 and 1.3 have no prerequisite.
(Sprint 3, forecast)3.1 E2E test suite (8), 3.2 Load test (5), 3.3 Feature-flag rollout (2)15All three depend on the payment adapters and 2.2, all complete by end of Sprint 2.

Velocity ceiling: 15 points/sprint (three-sprint average). Neither Sprint 1 nor Sprint 2 exceeds it, and no committed task precedes a dependency not scheduled in an earlier sprint.